Experience the power of results with Greendot Management Solutions

smed-changeover-reduction-pharma-case-study

SMED Changeover Reduction Pharma Case Study: Amazing 59% Cut

Your lines are busy all day, yet output never seems to match the hours you run. Shifts stretch, overtime becomes normal, and every product change eats half a shift. This SMED changeover reduction pharma case study shows how Eris Lifesciences, at its Guwahati plant, cut changeover time by up to 59% and now makes the same 10 crore tablets a month in 12 hours a day instead of 24, with zero overtime and without buying a single new machine.

At a glance

Client: Eris Lifesciences Ltd, listed Indian pharma company (ranked #21 in the Indian Pharmaceutical Market), WHO-GMP oral solid dosage plant in Guwahati, Assam. Problem: changeovers ate 12–32% of line time, 5S score of 14 out of 100, no Kaizen culture, 24-hour running with heavy overtime. What Greendot did: a 3-pillar Lean manufacturing programme: 5S, Kaizen and SMED (Single Minute Exchange of Die) on the production floor. Duration: 8 months. Result: changeover time down up to 59%, same monthly output in half the running hours, overtime eliminated, ₹17.9 lakh a year in documented Kaizen savings.

Up to 59%
shorter changeovers
24h → 12h
same 10 crore tablets a month
Zero
overtime (was 28% of the budget)
₹17.9 L
a year from 7 Kaizens

About the Client

Eris Lifesciences Ltd is a publicly listed Indian pharmaceutical company focused on domestic branded formulations, ranked #21 in the Indian Pharmaceutical Market. Founded in 2007, it is strong in cardio-metabolic care, and chronic and sub-chronic therapies make up most of its business. Its WHO-GMP certified plant in Guwahati, Assam makes oral solids (tablets and capsules) through granulation, compression, coating, capsule filling and strip packing lines. Learn more at eris.co.in.

The Challenge: Long Changeovers, Long Hours, No Improvement Culture

As sales grew, the plant ran 24 hours a day to keep up. The symptoms were clear, but the causes were spread across the workplace, the people and the process:

  • Changeovers were eating the day. Granulation lost 26% of available time to changeovers (average 200 minutes), compression lost 32% (average 300 minutes) and packing lost 12% (average 200 minutes).
  • The workplace was not under control. 5S awareness was almost nil. No visual controls, no standard practices. The first 5S assessment scored 14 out of 100.
  • No culture of improvement. Kaizen activity was nearly absent (engagement score of 2 at baseline). Operators had little exposure to waste-reduction thinking.
  • Hours and overtime kept rising. To meet a monthly output of 10 crore tablets, the plant ran round the clock, and overtime made up 28% of the budget.

Does this sound like your plant? If adding hours is the only way you know to add output, the lost capacity is usually hiding inside your changeovers.

pharma-changeover-loss-baseline

Our Approach: 5S, Kaizen and SMED as One Programme

Greendot ran the three pillars in sequence, each building on the one before, over 8 months on the live production floor, without stopping supply.

PillarWhy first / nextWhat we didOutput
1. 5SNo improvement lasts in a disorganised workplace5S training at every level on Sort, Set in Order and Shine; daily ‘1-Minute Sort’ and ‘5-Minute Shine’; red and yellow tags; PEEP (a Place for Everything, Everything in its Place); cleaning and inspection routines91 One Point Lessons (OPLs); QA department 5S self-assessment 15 out of 15
2. KaizenTurns operators from bystanders into problem-solversAwareness sessions on waste, flow and root cause; guided Kaizen workshops; a tracking and reward system38 Kaizens done, 11 with direct cost impact
3. SMEDBiggest capacity gain, once 5S and Kaizen habits existTimed each changeover step by step; split internal and external tasks; standardised procedures; parallel executionChangeover time down 26–59% on 6 lines

How SMED worked on the floor

SMED (Single Minute Exchange of Die) asks one question for every changeover step: does the machine really have to stop for this? Our consultants worked with operators on each line:

  1. Record and split. Every changeover was timed step by step and each step marked as internal (machine must stop) or external (can be done while the machine runs).
  2. Move work outside the stop. Tools, change parts, documents and line clearance material were made ready before the line stopped.
  3. Standardise. Each line got a written changeover sequence and a ready-kit, captured in One Point Lessons so every shift does it the same way.
  4. Work in parallel. Operators work side by side on a clear split of tasks, instead of one person doing every step in turn.

Changeover results by line

LineBeforeAfterReduction
Strip Packing I220 min90 min59% (best result)
Coating II180 min87 min52%
Compression300 min180 min40%
Granulation IV5 hours3 hours40%
Capsule Filling I180 min110 min39%
Granulation II240 min177 min26%

Across 19 machines, the plant now saves about 525 minutes of production time every day. Over a month that is roughly 260 hours, about 10 extra days of round-the-clock production, from the same machines and the same people.

Are changeovers eating your shifts?

Book a free 30-minute Changeover Loss Check. Share the changeover times of your top 3 machines and we will show you how much capacity is hiding in them.

Book a Free Changeover Loss Check
smed-changeover-reduction-pharma

Results After 8 Months

KPIBeforeAfterChange
Plant running hours for 10 crore tablets a month24 hrs/day12 hrs/daySame output in half the hours
Overtime28% of the budgetNilEliminated
Compression changeover300 min180 min−40%
Best changeover (Strip Packing I)220 min90 min−59%
Production time saved (19 machines)–525 min/day≈ 10 extra production days a month
Utility cost₹25.6 lakh₹9.3 lakh−64%
5S score14 / 100 (plant)15 / 15 (QA dept self-assessment)Audit-ready workplace
Kaizens implementedAlmost none38 (11 with cost impact)–

Where the ₹17.9 lakh a year came from

KaizenWhat changedAnnual saving
HPLC solvent optimisationBetter control of solvent use in the QC lab₹9,47,175
Yield improvement, Tendia MClosed-system handling cut raw material loss; yield rose from 93.91% to 97.71%₹3,17,489
Polybag usagePackaging material rationalised₹1,60,650
Cooling tower energySystematic cooling optimisation₹1,42,715
Swab samplingSampling frequency reduced; 820 hours a year saved₹1,39,460
A4 paper₹3,680 a month less paper₹44,160
QMS document processingWaiting time cut; 525 hours a year saved₹39,000
Total₹17,90,649
How we counted. The ₹17.9 lakh is the sum of the documented annual savings of the 7 Kaizens above. The utility cost reduction and the overtime that was eliminated are shown separately and are not added into this figure, so nothing is counted twice.

On the shop floor: a cleaner, safer, audit-ready plant that impresses regulators and customers, and operators who now suggest improvements themselves.

pharma-kaizen-savings

In the Client’s Words

In a video conversation with Greendot founder Nirav Trivedi, Rakesh Mahajan, Production Head at the Eris Lifesciences Guwahati plant, explained that none of these results needed new machinery or extra manpower. The change came from a new way of looking at the process and from applying Lean tools to the machines and people the plant already had.

What Made It Work

  • Foundation first. 5S came before SMED. Changeover kits and standard steps only work when every tool has a fixed place.
  • Operators owned the change. The people who run the lines timed their own changeovers and wrote the new steps, so they trusted and kept them.
  • Small daily habits. ‘1-Minute Sort’ and ‘5-Minute Shine’ built the discipline that big projects depend on.
  • Knowledge captured. 91 One Point Lessons mean every shift does the best method, not its own method.
  • Measured every week. 5S scores, Kaizen completion and changeover times were tracked on simple KPI boards.

Is Your Plant Facing the Same Problem?

Ask yourself these four questions:

  1. Do you know the average changeover time on your top 3 machines, in minutes?
  2. What share of your available line time goes into changeovers each month?
  3. Are you adding shifts or overtime to meet output, instead of using the hours you already have?
  4. Does every shift change over the same way, from a written standard?

If two or more answers are “no” or “not sure”, there is capacity locked inside your changeovers. Greendot has helped manufacturers across India with Lean manufacturing, 5S, Kaizen, SMED and TPM since 1999, as NPC and QCI approved Lean consultants. See our SMED consulting, 5S system and Kaizen implementation services, or the full lean manufacturing consulting page.

Want the same output from fewer hours?

Send us a message on WhatsApp. In a free 30-minute Changeover Loss Check we look at your changeover times and line hours and show you the first three actions to take.

Talk to Greendot on WhatsApp

SMED and Lean in Pharma: Frequently Asked Questions

What is SMED in pharmaceutical manufacturing?

SMED (Single Minute Exchange of Die) is a Lean method to cut changeover time. Each changeover step is marked internal (machine must stop) or external (can be done while it runs), external work is moved outside the stop, and the remaining steps are standardised. At Eris Lifesciences it cut changeovers by 26–59%.

How much can changeover time be reduced in a pharma plant?

In this case study, Strip Packing I went from 220 to 90 minutes (59%), Coating II from 180 to 87 minutes (52%) and Compression from 300 to 180 minutes (40%), on the same machines.

Is SMED allowed under GMP and line clearance rules?

Yes. SMED does not skip any line clearance or cleaning step. It prepares tools, change parts and documents before the stop and organises the work so that the required GMP steps are done faster and the same way every time.

Do you need new machines to reduce changeover time?

No. Eris Lifesciences got its results without new machinery or extra people. The gains came from 5S, standard work, One Point Lessons and parallel working by operators.

How long does a lean manufacturing programme take in pharma?

This 5S, Kaizen and SMED programme ran for 8 months on the live production floor, without stopping supply.

How do I start reducing changeover time in my plant?

Book a free 30-minute Changeover Loss Check with Greendot on WhatsApp at +91 90237 28317. Share the changeover times of your top 3 machines and we will show you where the biggest gain is.