Every new block, every capex project, adds more spares to your engineering store, and nothing ever leaves. This engineering inventory case study shows how a specialty chemicals plant in western India cut its spares stock from ₹64 Cr to ₹44.5 Cr in 10 months while breakdowns caused by missing spares fell by 45%, and without touching a single safety-critical spare.
At a glance
Client: multi-product specialty chemicals plant, western India (6 production blocks).
Problem: ₹64 Cr of engineering inventory, 21,600 item codes, ₹9.4 Cr of project leftovers and too many variants of the same part.
What Greendot did: ring-fenced safety spares, cleared project surplus, standardised gaskets, valves and seals, pooled spares across blocks and started a repair-first loop.
Duration: 16-week study and design + 6 months implementation support.
Result: inventory −30%, variants in 5 key families −59%, breakdown hours from missing spares −45%.
About the Client
A multi-product specialty chemicals manufacturer in western India with 6 production blocks: stainless steel and glass-lined batch reactors, solvent recovery, utilities (boilers, chillers, cooling towers) and effluent treatment. Its engineering stores held 21,600 active item codes worth ₹64 Cr: pumps, valves, mechanical seals, gaskets, instruments, flameproof motors, piping, and glass-lined and PTFE-lined parts.
The Challenge: Stock Grew With Every New Block and Every Project
Engineering inventory had grown 2.3 times in 5 years while production grew only 1.4 times. Each new block brought its own spares and its own preferred makes, and nobody removed the old ones. In the first 3 weeks we found:
- Project leftovers inside stores. ₹9.4 Cr of material bought for capex projects (pipes, valves, cable, structural steel) had come back to engineering stores after commissioning, with no review.
- Too many variants. 1,840 gasket codes and 3,250 valve codes. Different blocks had specified different makes, ratings and materials for the same duty.
- Unclear material of construction (MOC). 2,300 codes for SS316, Hastelloy and PTFE-lined items had no material grade in the description, so planners overstocked to be safe.
- Safety spares mixed with everything else. Safety valves, rupture discs and flameproof motor spares had no separate tag. Some were short, others in excess.
- Duplicate codes. About 3,000 codes (14%) repeated an existing part.
- No repair loop. Failed mechanical seals and pump parts were scrapped and bought new, though many could be reconditioned at 30–40% of new cost.
The cost: only ₹27.6 Cr of the ₹64 Cr had been used in the last 12 months. 28% of purchase value was emergency buying, and missing spares caused 186 hours of breakdowns a year.
Does this sound like your plant? If your engineering store grows faster than your production, the cause is rarely the stock norm. It is what enters the store and never leaves.
Our Approach: 5 Phases
| Phase | Weeks | What we did | Output |
|---|---|---|---|
| 1. Diagnose | 1–3 | ERP data pull (36 months), stores walk, ageing analysis, project surplus scan | Baseline and savings opportunity sized in ₹ |
| 2. Clean and classify | 3–7 | Merged duplicates; corrected material grades (PMI testing on doubtful alloy items); tagged every code ABC, VED, FSN, SDE, HML | Clean item master with class and grade on every code |
| 3. Standards and norms | 6–12 | Variety reduction family by family; approved-makes list; pooled Min-Max and safety stock for 6,200 A and B codes | Standard specifications and new norms in the ERP |
| 4. Surplus clearance | 8–16 | Project surplus reused, sold or returned; disposal committee for obsolete stock | Project surplus and dead stock cleared in batches |
| 5. Sustain | Months 5–10 | KPI dashboard, monthly review, seal reconditioning loop, training | A review system the plant runs itself |
Project surplus was tackled from week 8, before the norms were final, because it needed no new policy, only a decision. Savings started showing by month 3.
Safety first: statutory spares ring-fenced
Before any reduction, process safety fixed a list of statutory and safety spares that the project would never touch:
| Category | Examples | Policy |
|---|---|---|
| Statutory / safety | Pressure safety valves, rupture discs, flame arrestors, flameproof motor spares, gas detector sensors | Minimum set by process safety; never reduced without formal Management of Change approval; checked monthly |
| Vital, long lead time | Agitator mechanical seals, glass-lined reactor parts, Hastelloy items | 99% service level; one stock per type, shared across blocks |
| Essential | Standard pumps, valves, motors | Min-Max at 95%; pooled across blocks |
| Consumables | Gaskets, fasteners, PTFE sleeves, hoses | Rate contract and vendor consignment |
| Repairable | Mechanical seals, pump casings, gearboxes | Recondition first; buy new only if repair fails |
What the data showed
| Age since last issue | Value (₹ Cr) | Share |
|---|---|---|
| Used in last 12 months | 27.6 | 43% |
| 12–24 months | 10.2 | 16% |
| 24–36 months | 7.1 | 11% |
| Over 36 months | 9.7 | 15% |
| Project surplus (never issued) | 9.4 | 15% |
| Total | 64.0 | 100% |
ABC showed 8% of codes held 68% of consumption value. VED tagged 9% of codes Vital (2% statutory). Crossing movement with criticality gave 1,140 codes that were both Vital and non-moving; each was checked with process safety, and none was disposed of without sign-off.
Standardisation: one standard per duty
- Group all codes in a family by duty: size, pressure rating, temperature, chemical service.
- Pick one standard per duty (material grade, make, rating), agreed with engineering and process safety.
- Freeze buying of non-standard variants and use up existing stock first.
- Re-code the standard item and block the old codes in the ERP.
Example: gaskets for the same 2-inch, 150-class solvent line had 23 codes. They became 2.
Training and ownership
Block heads, engineers, stores and purchase teams were trained on the new standards, criticality rules and the repair-first loop. Process safety owned the statutory list, so nobody feared the reduction.
Is your engineering store growing faster than your plant?
Book a free 30-minute Inventory Gap Check. We look at your engineering stock, item codes, project surplus and stockouts, and show where the biggest saving is likely to be.
Book a Free Inventory Gap CheckResults After 10 Months
| KPI | Before | After (month 10) | Change |
|---|---|---|---|
| Engineering inventory value | ₹64 Cr | ₹44.5 Cr | −₹19.5 Cr (−30%) |
| Active item codes (net) | 21,600 | 14,900 | −6,700 (−31%) |
| Variants in 5 key families | 9,900 | 4,060 | −59% |
| Breakdown hours due to missing spares | 186 hrs/yr | 102 hrs/yr | −45% |
| Emergency purchases (share of PO value) | 28% | 11% | −17 points |
| Non-moving stock >24 months (excl. approved critical spares) | ₹16.8 Cr | ₹4.9 Cr | −71% |
Where the ₹19.5 Cr reduction came from
| Source | ₹ Cr |
|---|---|
| Project surplus: reused on running projects ₹4.1 Cr, sold ₹1.4 Cr, returned to vendors ₹1.3 Cr | 6.8 |
| Right-sized norms and pooling across blocks (includes ₹1.8 Cr of non-moving stock used in maintenance instead of buying new) | 4.6 |
| Variety reduction (fewer variants) | 2.3 |
| Gaskets and fasteners moved to vendor consignment | 1.6 |
| Obsolete stock cleared by auction, scrap or buy-back (write-off) | 4.2 |
| Total reduction | 19.5 |
Of the ₹16.8 Cr of non-moving stock, ₹5.9 Cr was confirmed as genuine critical or statutory spares and kept on purpose.
What Made It Work
- Safety first, visibly. Process safety owned the statutory list and signed every decision on Vital items, so the reduction never put people or the plant at risk.
- Stop the inflow, not just the stock. Every capex project now closes with a material reconciliation; leftovers go back to the project’s cost centre, not to engineering stores.
- Fewer variants, shared stock. One standard per duty and one common stock per type across blocks.
- Rules that stay. Material grade and criticality are mandatory ERP fields, a master data cell checks every new code, an approved-makes list guides buying, and a monthly one-page KPI review keeps it on track.
People problems we solved
| Challenge | What we did |
|---|---|
| “Lower stock will hurt process safety” | Statutory and safety spares ring-fenced by process safety; never in the reduction pool |
| Each block wanted its own spares | Showed the pooling maths (12 seals vs 5) to block heads; common-stock bins with same-day issue |
| Unclear material grade on old codes | Physical check with engineers and PMI testing on doubtful alloy items |
| Project teams did not want to return material | Material reconciliation added to project closure |
| Finance cautious about write-offs | Disposal committee with clear rules and quarterly batches |
Is Your Plant Facing the Same Problem?
Ask yourself these four questions:
- How much material from your last 3 capex projects is still sitting in engineering stores?
- How many different gasket and valve codes do you use for the same duty?
- Are your statutory and safety spares tagged and protected separately?
- Do you recondition failed seals and pump parts, or always buy new?
If two or more answers worry you, there is money locked in your engineering store, and possibly a safety gap too. Greendot has worked with 1,200+ manufacturers since 1999 on Lean, 5S, TPM and inventory reduction. See our inventory reduction consulting service.
Want to know how much engineering inventory you can safely release?
Send us a message on WhatsApp. In a free 30-minute Inventory Gap Check we review your stock, codes, project surplus and stockouts and show you the first three actions to take.
Talk to Greendot on WhatsAppEngineering Inventory Reduction: Frequently Asked Questions
How do you reduce engineering inventory in a chemical plant without risking safety?
Ring-fence statutory and safety spares first. In this plant, process safety fixed the minimum stock of safety valves, rupture discs and flameproof spares, and those items were never in the reduction pool. Engineering inventory still fell 30%, from ₹64 Cr to ₹44.5 Cr.
What is variety reduction in spare parts?
It means cutting the number of different makes, sizes and materials used for the same duty. In this plant, codes in 5 key families (valves, fasteners, gaskets, bearings, mechanical seals) fell from 9,900 to 4,060, a 59% reduction.
What should a plant do with project surplus material?
Review it at project closure. Reuse it on running projects first, then return it to vendors or sell it. Here ₹6.8 Cr of ₹9.4 Cr project surplus left the books within 5 months, and a material reconciliation rule now stops new surplus building up.
Does pooling spares across blocks increase risk?
No. One plant-wide stock gives better protection than separate stocks per block. For a Vital agitator seal, 5 seals held plant-wide give 99.6% protection, compared with 12 seals split across 4 blocks before.
How long does an engineering inventory reduction project take?
This project took a 16-week study and design phase plus 6 months of implementation support. Savings started showing by month 3, because project surplus needed only a decision, not a new policy.
How do I start an inventory review for my chemical plant?
Book a free 30-minute Inventory Gap Check with Greendot on WhatsApp at +91 90237 28317. We review your engineering stock, item codes, project surplus and stockouts and show where the biggest saving is likely to be.