Your stores are full, yet maintenance still waits for spares. Every month the inventory number goes up, and every week a machine stops because one part is missing. This spares inventory case study shows how an integrated pulp and paper mill in India broke that cycle: it cut inventory by ₹47 Cr in 12 months while its critical spares became more available, not less.
At a glance
Client: integrated pulp, paper and paperboard mill, India (about 1,000 tonnes per day, 3 paper machines). Problem: ₹186 Cr of inventory, 38,400 item codes, 20+ emergency purchases a week. What Greendot did: classified every code (ABC, VED, FSN, SDE, HML), wrote a criticality-based spares policy, reset Min-Max and safety stock in the ERP, and cleared dead stock. Duration: 20-week study and design + 6 months implementation support. Result: inventory ₹186 Cr → ₹139 Cr, critical spares availability 87% → 97%, breakdown hours from missing spares −41%.
About the Client
An integrated pulp, paper and paperboard mill in India, producing about 1,000 tonnes per day on 3 paper machines, with its own chemical recovery plant, captive power plant and wood yard. Its stores held 38,400 active item codes, of which ₹142 Cr was spares and MRO (Maintenance, Repair and Operations) items, spread across 6 main stores and 11 informal sub-stores near the machines.
The Challenge: High Stock, Yet Machines Still Waited for Spares
Management’s question was simple: “Why do we have so much stock and still run out of the parts we need?” In the first 4 weeks we found six problems feeding each other:
- No criticality data. No item code carried a VED or criticality tag. A ₹400 gasket and a ₹38 lakh recovery boiler spare were ordered under the same logic.
- Outdated ERP norms. 71% of reorder levels in SAP had not been reviewed in 5+ years; lead times were system defaults, not real supplier lead times.
- Duplicate codes. About 6,900 codes (18%) were the same part under a different description, for example “BRG 22320” and “Bearing SKF 22320 CCK/W33”.
- Hidden stock. 11 informal sub-stores held issued-but-unused material worth about ₹8 Cr, outside the books.
- Dead stock nobody owned. ₹38 Cr had not moved for over 3 years, including spares for equipment already scrapped.
- Over-bought paper machine clothing. 3–4 sets of wires and felts per machine, against a need of 1–2.
The cost: money locked in stock that earned nothing, 23% of purchase value spent on emergency buying, and 412 hours a year of breakdowns caused by spares that were not available. Stores tracked value, maintenance tracked breakdowns and finance tracked working capital, so nobody owned the trade-off.
Does this sound like your plant? If your inventory keeps growing and your machines still wait for parts, the problem is usually not the quantity of stock. It is the logic behind it.
Our Approach: 5 Phases
| Phase | Weeks | What we did | Output |
|---|---|---|---|
| 1. Diagnose | 1–4 | ERP data pull (36 months), stores walk, interviews with stores, maintenance, purchase and finance | Baseline and savings opportunity sized in ₹ |
| 2. Clean and classify | 3–9 | Merged 6,900 duplicate codes; tagged every code ABC, VED, FSN, SDE, HML; equipment criticality workshops | Clean item master with a class on every code |
| 3. Policy and norms | 8–14 | Stocking strategy per class; new Min-Max, reorder point and safety stock for 9,800 A and B codes; approved insurance spares list | Spares policy and new norms loaded in the ERP |
| 4. Dead stock clearance | 12–20 | Disposal committee, internal reuse, vendor returns, quarterly auctions | Non-moving stock cleared in batches |
| 5. Sustain | Months 6–12 | KPI dashboard, Monthly Inventory Review chaired by the plant head, stores SOPs, training | A review system the mill runs itself |
Phases overlap on purpose. Quick wins (duplicate merging, sub-store returns) showed from month 1; the big reductions came after the new norms went live in the ERP in month 3.
What the data showed
Five classifications, each answering one management question, gave every item code a clear “how to manage” tag:
| Analysis | Question it answers | What we found |
|---|---|---|
| ABC | Where is the money? | 3,456 A class codes (9%) = 71% of annual consumption value |
| VED | What must never run out? | 11% Vital, 34% Essential, 55% Desirable |
| FSN | What is not moving? | 55% of codes non-moving, holding ₹38 Cr (27% of spares value) |
| SDE | What is hard to buy? | 9% Scarce, mostly imported paper machine and recovery boiler spares |
| HML | Who approves what? | High-price items need plant head approval before ordering |
The key insight came from crossing FSN with VED: about ₹9.8 Cr of “non-moving” stock was Vital insurance spares that must stay. Everything else non-moving could safely go.
Spares policy: criticality decides how much to stock
| Class | Example spares | Stocking strategy |
|---|---|---|
| Vital + high value | Recovery boiler tubes, refiner rotor, dryer gearbox | Hold 1 set as insurance spare, approved by plant head, reviewed yearly |
| Vital + low/medium value | Critical bearings, mechanical seals, DCS cards, doctor blades | Min-Max at 98–99% service level |
| Essential | Pump impellers, valves, motors up to 75 kW | Min-Max at 95%; pooled across the 3 machines |
| Desirable + high value | Large castings, special fabrications | Do not stock; make-to-order with drawings ready |
| Desirable + low value | Fasteners, general hardware, PPE | Rate contract / vendor-managed inventory |
| Paper machine clothing | Forming wires, press felts | Vendor consignment; call-off 3 weeks before change |
Setting the right stock level
Norms for 9,800 A and B codes were recalculated from 3 years of actual consumption and real supplier lead times (taken from purchase order and goods receipt dates, not ERP defaults).
Safety stock = 1.65 × 1.8 × √1.5 = 3.6 → 4 · Reorder point = (4 × 1.5) + 4 = 10 · Max = 10 + quarterly order of 8 = 18.
Old norm Min 20 / Max 40 → new norm Min 10 / Max 18.
Dead stock: one decision tree for every item
- Is the parent equipment still in the plant? If not: reuse elsewhere, return to the vendor, or auction.
- Is it Vital with a long lead time? If yes: keep it as an approved insurance spare.
- Can another machine or a project use it? If yes: transfer it internally (₹6.2 Cr was reused this way).
- Will the vendor take it back? If yes: negotiate a buy-back or credit.
Training and ownership
Criticality was scored by the mill’s own maintenance engineers in workshops, so they trusted the new norms. 46 stores, purchase and maintenance staff were trained on the new classification, norms, stores SOPs and the master data rules.
Is your inventory growing while machines still wait for spares?
Book a free 30-minute Inventory Gap Check. We look at your stock value, item codes and stockouts, and tell you where the biggest saving is likely to be.
Book a Free Inventory Gap CheckResults After 12 Months
| KPI | Before | After (month 12) | Change |
|---|---|---|---|
| Total inventory value | ₹186 Cr | ₹139 Cr | −₹47 Cr (−25%) |
| Inventory turns per year | 1.9 | 2.6 | +37% |
| Critical spares available when needed | 87% | 97% | +10 points |
| Breakdown hours due to missing spares | 412 hrs/yr | 243 hrs/yr | −41% |
| Non-moving stock (excl. approved insurance spares) | ₹38 Cr | ₹7.3 Cr | −81% |
| Duplicate item codes | 18% | Under 2% | −16 points |
| Emergency purchases (share of PO value) | 23% | 9% | −14 points |
Where the ₹47 Cr reduction came from
| Source | ₹ Cr |
|---|---|
| Right-sized Min-Max on active A and B items | 15.4 |
| Dead stock reused in the plant | 6.2 |
| Paper machine clothing moved to vendor consignment | 6.1 |
| Common spares pooled across 3 machines | 4.6 |
| Dead stock returned to vendors / buy-back | 3.1 |
| Obsolete stock cleared by auction or scrap (write-off) | 11.6 |
| Total reduction | 47.0 |
On the shop floor: breakdown hours caused by missing spares fell from 412 to 243 a year, mainly because Vital spares are now stocked to a 98–99% service level instead of by habit.
What Made It Work
- Criticality first, cost second. Stock was cut on non-critical items first; Vital items got a higher service level. No norm was cut by more than 50% in one step.
- Maintenance owned the decisions. Engineers scored criticality themselves, so they trusted and used the new norms.
- Real data, not ERP defaults. Real lead times from 3 years of purchase records changed thousands of reorder points.
- A system that outlasts the consultant. A master data cell (no new code without a duplicate check), a Monthly Inventory Review chaired by the plant head with 8 KPIs on one page, a quarterly disposal committee and a yearly norm review.
People problems we solved
| Challenge | What we did |
|---|---|
| “Less stock means more breakdowns” | Vital items protected first; critical spares availability tracked weekly from month 1 |
| Hidden sub-stores on the shop floor | “Amnesty week”: material returned with no questions asked; ₹8 Cr came back on the books |
| Finance hesitant to write off | Disposal committee with clear rules (age, equipment status, realisable value), decisions in quarterly batches |
| Buyers ordering by habit | ERP auto-requisition for C items; any order above Max needs Head – Materials approval |
Is Your Plant Facing the Same Problem?
Ask yourself these four questions:
- Do you know which 10% of your item codes hold most of your inventory value?
- Does every spare carry a criticality tag (Vital, Essential, Desirable)?
- When were your reorder levels last recalculated with real supplier lead times?
- How much of your stock has not moved for 2–3 years, and who owns that decision?
If two or more answers are “no” or “not sure”, there is money and machine uptime locked in your stores. Greendot has worked with 1,200+ manufacturers since 1999 on Lean, 5S, TPM and inventory reduction. See our inventory reduction consulting service.
Want to know how much inventory your plant can safely release?
Send us a message on WhatsApp. In a free 30-minute Inventory Gap Check we review your stock, codes and stockouts and show you the first three actions to take.
Talk to Greendot on WhatsAppWhat Made It Work
- Criticality first, cost second. Stock was cut on non-critical items first; Vital items got a higher service level. No norm was cut by more than 50% in one step.
- Maintenance owned the decisions. Engineers scored criticality themselves, so they trusted and used the new norms.
- Real data, not ERP defaults. Real lead times from 3 years of purchase records changed thousands of reorder points.
- A system that outlasts the consultant. A master data cell (no new code without a duplicate check), a Monthly Inventory Review chaired by the plant head with 8 KPIs on one page, a quarterly disposal committee and a yearly norm review.
People problems we solved
| Challenge | What we did |
|---|---|
| “Less stock means more breakdowns” | Vital items protected first; critical spares availability tracked weekly from month 1 |
| Hidden sub-stores on the shop floor | “Amnesty week”: material returned with no questions asked; ₹8 Cr came back on the books |
| Finance hesitant to write off | Disposal committee with clear rules (age, equipment status, realisable value), decisions in quarterly batches |
| Buyers ordering by habit | ERP auto-requisition for C items; any order above Max needs Head – Materials approval |
Is Your Plant Facing the Same Problem?
Ask yourself these four questions:
- Do you know which 10% of your item codes hold most of your inventory value?
- Does every spare carry a criticality tag (Vital, Essential, Desirable)?
- When were your reorder levels last recalculated with real supplier lead times?
- How much of your stock has not moved for 2–3 years, and who owns that decision?
If two or more answers are “no” or “not sure”, there is money and machine uptime locked in your stores. Greendot has worked with 1,200+ manufacturers since 1999 on Lean, 5S, TPM and inventory reduction. See our inventory reduction consulting service.
Want to know how much inventory your plant can safely release?
Send us a message on WhatsApp. In a free 30-minute Inventory Gap Check we review your stock, codes and stockouts and show you the first three actions to take.
Talk to Greendot on WhatsAppSpares Inventory Reduction: Frequently Asked Questions
How much can a paper mill reduce its spares inventory?
In this integrated pulp and paper mill, total inventory fell 25% in 12 months, from ₹186 Cr to ₹139 Cr. Non-moving spares fell from ₹38 Cr to ₹7.3 Cr, and critical spares availability still rose from 87% to 97%.
Will reducing spares inventory increase machine breakdowns?
Not if you start with criticality. Vital spares were moved to a 98–99% service level and stock was cut first on non-critical items. Breakdown hours caused by missing spares fell from 412 to 243 a year.
What is ABC-VED analysis in spares management?
ABC groups items by annual consumption value (where the money is). VED groups them by the impact of a shortage: Vital, Essential, Desirable. Combining the two decides how tightly to control each item. In this mill, 9% of codes drove 71% of consumption value.
How long does a spares inventory reduction project take?
This project took a 20-week study and design phase, then 6 months of implementation support. Quick wins showed from month 1 and the large reductions came after new norms went live in the ERP in month 3.
Does inventory reduction disrupt production?
No. Norms were reduced in steps of no more than 50%, Vital spares were protected first, and critical spares availability was tracked every week. Availability went up from 87% to 97% during the project.
How do I start an inventory review for my plant?
Book a free 30-minute Inventory Gap Check with Greendot on WhatsApp at +91 90237 28317. We review your stock value, item codes and stockouts and tell you where the biggest saving is likely to be.