Spares Inventory in a Paper Mill: How the Mill Cut Stock by ₹47 Cr

How an integrated pulp and paper mill cut inventory from ₹186 Cr to ₹139 Cr in 12 months while critical spares availability rose from 87% to 97%.
Engineering Spares in a Chemical Plant: How the Plant Cut Inventory by 30%

Every new block, every capex project, adds more spares to your engineering store, and nothing ever leaves. This engineering inventory case study shows how a specialty chemicals plant in western India cut its spares stock from ₹64 Cr to ₹44.5 Cr in 10 months while breakdowns caused by missing spares fell by 45%, and without […]
5S in a Chemical Plant: How Willowood Built a Safer Dahej Plant

Result of 5s at a glance at Willowood 9% → 73%5S audit score (Nov 2024 – Nov 2025) 6,000+Unwanted items removed 288 / 295Red tags closed (97.6%) 144Zones with visual controls Project details Client Willowood Industries Pvt. Ltd. Industry Agrochemicals – technical (active ingredient) manufacturing Location Dahej, Bharuch, Gujarat Service 5S implementation, visual management and […]
PMS in a Chemical Company: How Hema Dye Chem Tripled Performance

This performance management system case study shows how GreenDot designed and implemented KPI and KRA systems for 100% of employees at Hema Dye Chem — moving the company from no formal reviews to monthly, data-driven performance discipline. 18% → 56%Performance accountability score (May–Dec 2025) 13.47% → 38.24%Company efficiency 100%Employees covered by KPIs and KRAs 80%+Preventive […]
5S in an Agrochemical Plant: How Heranba Industries Recovered ₹43+ Lakh

f
Increase Sales Case Study: 29 → 9 Days, +30% Sales | Greendot

How DG Industries, a 30-person material handling equipment maker in Valsad, cut production lead time from 29 to 9 days and grew sales 30% in 18 months with VSM, 5S, Kaizen and sales tracking.
Lead Time Reduction in Machine Building: How Kairish Innotech Cut Delivery Time from 402 to 209 Days

How Kairish Innotech, a special purpose machine builder in Daman, cut machine-building lead time from 402 to 209 days in about 12 months with value stream mapping, design freeze and DFMEA.
SMED Changeover Reduction Pharma Case Study: Amazing 59% Cut
How Eris Lifesciences, Guwahati cut changeover time by up to 59%, made the same 10 crore tablets a month in 12 hours a day instead of 24, and ended overtime, with no new machines.
Copper Extrusion OEE Case Study: +50% Output | Greendot

How New India Cuprotec, a copper extrusion plant in Silvassa, raised output per working day from 16.4 to 24.5 tonnes on the same four machines with OEE, SMED and kaizen.
Sales Growth Case Study: Alltech ₹38 Cr → ₹158 Cr | Greendot

Alltech India grew sales from ₹38 Cr to ₹158 Cr in 4 years with positioning, CRM, value selling and a monthly review system.
Customer Satisfaction Reducing Service Complaints

Executive SummaryThis case study examines how a leading Indian heavy engineering manufacturer (referred to as “Company A” due to NDA restrictions) applied Value Engineering (VE) methodology to reduce the life-cycle costs of hydraulic actuation systems for specialized industrial equipment. Through systematic function analysis and creative problem-solving, the VE team achieved a 23% reduction in maintenance […]
Transforming AeroBlue Footwear: How Lean Manufacturing Delivered a 20% Boost in Productivity and Faster Delivery

Achieved 20% Higher Productivity and 30% Faster Deliveries by Eliminating Production Bottlenecks through Lean Manufacturing Client Overview Challenges (Before Greendot) DAeroBlue Footwear faced multiple inefficiencies across its production operations: Our Approach Greendot designed a phased Lean implementation roadmap tailored for the footwear industry: Solutions Implemented Area Solution Workplace Organization Employee feedback loop and regular Lean […]
81% Faster Delivery and 50% Fewer Rejections: How R.S. Automation Transformed Efficiency through Lean Manufacturing

Reduced Delivery Lead Time by 81% and Cut Rejections by 50% through Lean Manufacturing and Continuous Improvement Culture Client Overview Challenges (Before Greendot) Despite its technical expertise and strong customer base, R.S. Automation Transformed faced significant operational inefficiencies: Our Approach Greendot developed a customised Lean Manufacturing Implementation Plan focused on productivity improvement, waste reduction, and […]
70% Fewer Accidents, 25% Higher Productivity: How RBD Engineers Saved 30 Lakhs through Lean Safety & Space Optimization

Reduced Workplace Accidents by 70% and Improved Productivity by 25% through Lean-Based Safety and Space Management Transformation Client Overview Challenges (Before Greendot) RBD Engineers faced dual challenges affecting both safety performance and production efficiency: Our Approach Greendot designed a Lean Manufacturing Implementation Program combining safety, layout optimisation, and visual management for measurable results: Continuous Monitoring: […]
Lean Manufacturing in Plastic Packaging: How Pack-Well Industries Cut Machine Downtime 25% and Freed 30% Floor Space

How Pack-Well Industries, a plastic packaging manufacturer in Valsad, cut machine downtime 25%, freed 30% floor space and ran 34 Kaizen events with 5S, TPM and Kanban.
90% Less Waste, 40% More Sales: How Jalaram Khichdi Transformed Its Restaurant Operations through Effective Management Consulting

Reduced Food Waste by 90% and Increased Sales by 40% through Leadership Development and Process Optimization Client Overview Challenges (Before Greendot) Jalaram Khichdi faced deep-rooted management and operational inefficiencies that were impacting profitability and morale: Our Approach Greendot implemented a comprehensive Management Consulting program focusing on leadership development, process improvement, and culture transformation: Solutions Implemented […]