Four modern extrusion machines, ISO 9001, 14001 and 45001 certificates, a growing order book, and still the plant made about 500 tonnes a month, year after year. This OEE improvement case study shows how New India Cuprotec (Coptec), a copper extrusion plant in Silvassa, raised output from 16.4 to 24.5 tonnes per working day on the same four machines. It did not buy a new press. It measured every lost minute, attacked the biggest loss first and changed how the shop floor works.

At a glance

Client: New India Cuprotec (Coptec, New India Group), Silvassa: copper busbars, strips, flats, profiles and rods made on four continuous rotary extrusion lines (TLJ-300, TLJ-350, TLJ-370, TLJ-400).

Problem: output stuck near 500 tonnes a month, no machine-level data, 48-minute changeovers and scrap above 12%. 

What Greendot did: a live OEE dashboard with 24 loss codes, speed standards for every machine, SMED on die changeover, a wheel-change kaizen, a die failure action plan and a shop-floor kaizen system. 

Period: started October 2022; results compare November 2022 with May 2023.

+50%
output per working day
(16.4 → 24.5 t)
50% → 59%
OEE on the plant dashboard
−34%
changeover time
(48 → 31 min)
12.3% → 9.0%
scrap and set-up rejection

The Problem: Good Machines, Flat Output

From 2018 to 2022 the extrusion department made between 440 and 535 tonnes a month on average. Orders were there. The machines were capable of more. But nobody could say where the hours went, because the only records were daily production and scrap totals.

What the plant looked like before the project

  • Output: 15.9 to 16.7 tonnes per working day from April to July 2022, about 500 tonnes a month.
  • Scrap: scrap and set-up rejection averaged 12.3% of output from January to October 2022, with months as high as 16.9%.
  • Changeover: about 790 die changeovers a month across four lines, averaging 48 minutes each, and 60 minutes on the TLJ-400.
  • Breakdowns: the maintenance team spent its days on breakdown work instead of prevention.
  • No visibility: no OEE, no loss codes, no speed standard. Decisions were made on experience.

In November 2022, the first month of proper measurement, the four lines lost 1,379 machine-hours. One loss stood far above the rest: changeover, at 628 hours (46%). That became target number one.

“पहले बहुत ब्रेकडाउन मेंटेनेंस आ रहा था, तो हम लोग बार-बार मेंटेनेंस में ही परेशान रहते थे।”
(Before, we kept getting breakdowns, so we were always stuck fixing machines.)

Gaurav, Mechanical Engineer, Maintenance, New India Cuprotec

copper-extrusion-machine-hours-lost-changeover.

What Greendot Did: Seven Steps, in This Order

The project ran as a weekly OEE meeting with the extrusion, die shop and maintenance teams in one room. Each step below came out of the data, not out of a template.

StepWhat we didWhy it mattered
1. Measure every minuteA 61-column daily log for each machine and shift: product, RPM, start and stop time, 24 loss codes, set-up rejection and process scrap. It feeds a live OEE dashboard reviewed every week.For the first time the plant could see availability, losses and scrap by machine, by day and by reason.
2. Set speed standardsRPM-wise output charts for each machine (for example TLJ-350: 7.8 kg/min at 6 RPM) and product standards for about 2,670 sizes, by width and thickness.Operators ran to a standard instead of a habit. Slow running showed up the same day.
3. SMED on die changeoverEach changeover broken into steps and split into internal, external and parallel work. The next die and chamber are heated in the oven before the stop. Fixed roles: 1 operator, 3 skilled workers, 1 helper from a running line.On TLJ-400 a trial in November 2022 cut one changeover from 41 to 24 minutes. The method then went to all four lines.
4. Remove waiting during changeoverOnly one changeover planned at a time so running-line operators can help; separate chamber fitting tables, a cutter at every machine, a zip crane for TLJ-400, drums marked and kept ready.Most of the lost minutes were people waiting for a tool, a crane or a drum, not the die change itself.
5. Wheel-change kaizenWheel life fixed by tonnage (TLJ-300: 300 t, TLJ-350: 170 t, TLJ-370: 150 t, TLJ-400: 240 t). Wheels changed on the Tuesday weekly off, not during running shifts.About 24 running hours a month that went into wheel changes now go into production.
6. Preventive maintenanceHeat exchanger and coining roll cooling projects, weekly Tuesday checks of coining roll alignment and DC motor filters, and a fixed preventive maintenance cycle.The maintenance team now guarantees 15 days without a major breakdown and is working towards 21.
7. Die failure action plan1,186 die failures logged and Pareto-analysed from December 2022 to April 2023 (lining, edge crack, under-size, centre minus, machine trip). Standards set for wheel-to-chamber gap, chamber heating time and die polishing.Die failures moved from “bad luck” to a list of causes with an owner for each.

The shop floor also wrote its own list. In October 2022 the team raised 28 improvement projects, from a spare chamber oven to crane lighting and scrap boxes. Each one was discussed in the OEE meeting, given a leader and closed on a standard kaizen sheet.

The OEE dashboard the team used every week

This is the plant’s own dashboard from the project. Every bar comes from the daily machine log, so arguments in the weekly meeting were settled by data.

oee dash board
smed changeover reduction copper extrusion

Results: What Changed in Seven Months

The figures below come from the plant’s dashboard and production records. Before figures are from 2022; after figures are from December 2022 to May 2023.

MeasureBeforeAfterChange
Output per working day16.4 t (Apr–Jul 2022)24.5 t (Dec 2022–May 2023)+50%
Monthly output500 t634 t average, best 678 t (Mar 2023)+27%, in 25–27 working days instead of 30–31
OEE (plant dashboard)50% (Nov 2022)59% (May 2023)+9 points
Average changeover47.7 min31.4 min−34%, about 205 machine-hours a month freed
Scrap and set-up rejection12.3% (Jan–Oct 2022)9.0% (Apr–May 2023)−3.3 points, about 20 t less to re-melt each month
Preventive maintenanceBreakdown driven15 days without a major breakdownNext target: 21 days

Hear it from the New India Cuprotec team

Gaurav, Maintenance: from breakdown firefighting to a 15-day guarantee of no major breakdown, with 21 days as the next target.

Production team: output was 15 to 18 tonnes a day before the project; the monthly average is now about 24 tonnes, and surface colour has improved.

“अभी हमारा मंथली 24 टन का एवरेज चालू है … और हमारा जो कलर है वह भी काफी चेंज हुआ है।”
(Our monthly average is now running at 24 tonnes a day … and our product colour has also improved a lot.)

Production team member, New India Cuprotec

copper extrusion daily output oee increase

Why It Worked

  • Data before decisions. The 61-column log looked like extra work in week one. By week four it was ending arguments in the OEE meeting.
  • Biggest loss first. Changeover was 46% of lost time, so SMED came before any new idea. One trial on TLJ-400 (41 to 24 minutes) convinced the team.
  • Small, cheap fixes. A cutter at every machine, a marked drum area, wheel changes on the weekly off. Almost none of it needed capital.
  • One team, not three. Extrusion, die shop and maintenance sat in the same weekly meeting and owned the same numbers.
  • Ownership on the floor. 28 projects came from operators and engineers, each with a named leader.

What we would tell another extrusion plant

  1. Separate planned shutdown from real losses, or your OEE will hide the problem.
  2. Measure changeover per machine. The TLJ-400 took twice as long as the TLJ-300, and that is where the hours were.
  3. Fix the speed standard for every size before you judge performance.
  4. Log every die failure with a reason. You cannot reduce what you only remember.

Is your plant losing hours you cannot see?

Book a free 30-minute OEE Check with Greendot. Share one month of production data and we will show you your biggest loss and where to start.

WhatsApp us: +91 90237 28317

Copper Extrusion OEE: Frequently Asked Questions

What is a good OEE for a copper extrusion plant?

World-class OEE is often quoted at 85%, but most Indian extrusion plants start between 40% and 60%. In this case study the plant moved from 50% to 59% in seven months, and output per working day rose 50%.

How did New India Cuprotec increase output without new machines?

By measuring every lost minute on its four extrusion lines, cutting changeover time 34% with SMED, setting speed standards for each machine and size, moving wheel changes to the weekly off and starting preventive maintenance. Output went from 16.4 to 24.5 tonnes per working day.

What is SMED and how does it apply to extrusion die changeover?

SMED (Single-Minute Exchange of Die) separates work that must be done with the machine stopped from work that can be done while it runs. Here the next die and chamber are heated in advance and each person has a fixed role, so the average changeover fell from 48 to 31 minutes.

How long does an OEE improvement project take?

The first results came within two months. In this case the plant started in October 2022, and by December 2022 output per working day had reached 25 tonnes. The results in this case study compare November 2022 with May 2023.

Does OEE work for continuous extrusion machines?

Yes. You track calendar time, stop reasons, output against a speed standard and scrap for each machine and shift. On continuous rotary extrusion lines the biggest losses are usually die changeover, wheel change, die failure and waiting for drums, cranes or material.

How can I start improving OEE in my plant?

Book a free 30-minute OEE Check with Greendot on WhatsApp at +91 90237 28317. Share one month of production and downtime data and we will show you your biggest loss and where to start.